Canadian Forest Products Ltd. – TFL 14

SN Forestry Operations Ltd – FLTC A82551

Audit of Forest Planning and Practices: SN Forestry Operations Ltd – Forest Licence to Cut A82551

In May 2016 the Forest Practices Board audited the activities of SN Forestry Operations Ltd.’s Forestry Licence to Cut A82551 in the Sea to Sky Natural Resource District. SN Forestry is owned by the Squamish Nation, and the licence permits it to harvest 592 800 cubic metres of timber from within the boundaries of Tree Farm Licence 38.

The results were good – SN Forestry’s operational planning, timber harvesting, road construction and maintenance, silviculture, and fire protection activities complied in all significant respects with the requirements of the Forest and Range Practices Act, the Wildfire Act and related regulations.

Selkirk Natural Resource District – Woodlot Licence W0437

Audit of Forest Planning and Practices: Selkirk Natural Resource District – Woodlot Licence W0437

As part of its 2015 compliance audit program, the Forest Practices Board selected woodlot W0437, held by Arrow Glenn Ltd., in the Selkirk District, for audit. The woodlot’s operations are located on north-east of Creston, along Highway 3.

The audit found, except for silviculture obligations and annual reporting, that planning and practices generally complied with the Forest and Range Practices Act (FRPA) and the Wildfire Act.

Arrow Glenn Ltd. did not meet FRPA requirements for regeneration delay, free growing or annual reporting on any of the cutblocks audited on woodlot W0437. Auditors found that the licensee did not meet the requirements within the required timeframes and did not conform to reporting standards for its annual reports. These combined significant non-compliances are of sufficient magnitude to warrant an overall adverse opinion.

Audit of Forest Planning and Practices: Selkirk Natural Resource District – Woodlot Licence W0436

As part of its 2015 compliance audit program, the Forest Practices Board selected woodlot W0436, held by Duncan Stanley Lake and Yvonne Boyd, in the Selkirk District, for audit. The woodlot’s operations are located on north-west of Meadow Creek, along Highway 31. The audit found, except for bridge maintenance and annual reporting, that planning and practices generally complied with the Forest and Range Practices Act and the Wildfire Act. The audit also identified an area requiring improvement related to riparian management. Auditors found a bridge with rot in its substructure, which is a potential safety hazard. The licensee had not assessed the bridge for load-bearing strength nor posted any load restriction or bridge approach signs. Because the licensee had not properly identified and posted the bridge deficiency, it created a safety hazard and is not in compliance with the Woodlot Licence Planning and Practices Regulation (WLPPR). Auditors also found the licensee did not meet submission deadlines or specification requirements for its annual reports. These practices were pervasive and do not provide assurance of good silviculture practices and therefore is considered a significant non-compliance. Auditors also found the licensee had re-classified a fish stream (S3) as non-fish bearing but had not collected enough information to support the classification. As such, the licensee should have managed the stream as if it was fish bearing, requiring a 20-metre riparian reserve zone. The licensee harvested trees in the riparian reserve zone and is non-compliant with the WLPPR. While minimal harm resulted, this practice elevated the risk of harm to fish or fish habitat and is considered an area requiring improvement.

Selkirk Natural Resource District – Woodlot Licence W0436

Selkirk Natural Resource District – Woodlot Licence W0438

Audit of Forest Planning and Practices: Selkirk Natural Resource District – Woodlot Licence W0438

As part of its 2015 compliance audit program, the Forest Practices Board selected woodlot W0438, held by Jeffrey Mattes, in the Selkirk District, for audit. The woodlot’s operations are located on south of Kaslo, along Highway 31.

The audit found that planning and practices generally complied with the Forest and Range Practices Act and the Wildfire Act. However, the audit also identified two areas requiring improvement related to fire hazard assessments and annual reporting.

 

Selkirk Natural Resource District – Woodlot Licences W1644